Projects

Completed Projects

Power lines in Kasese District

  1. Kikorongo-Bwera-Mpondwe with T-offs to:
  • Kiburara-Rwenguhya
  • Kinyamaseka-Munkunyu-Kanyampara
  • Kinyamaseke-Kasomoro
  • Katholhu-Bunyiswa-Kakone-Musyenene
  • Bwera-Kasanga
  • Bwera-Karambi
  • Lhubiriha-Kamasasa

2. Bugoye-Ibanda-Nyakalingijo with T-offs to Kyanya and Maliba TCs.

3. Rugendabara-Kitswamba-Kyabarungira with T-off to Kithoma.

There are three bulk metering units, one auto recloser unit and 59 transformer sub-stations in the electricity distribution network in Kasese District. The transformer sub-stations are detailed below.

  • 14 No. 25 kVA distribution transformers.
  • 29 No. 50 kVA distribution transformers.
  • 13 No. 100 kVA distribution transformers.
  • 1 No. 200 kVA distribution transformers.
  • 3 No. 315 kVA distribution transformers.
  • 1 No. 500 kVA distribution transformer.

Power lines in Ruburizi District

Kyambura-Katerera
The electricity distribution network in Rubirizi District consists of 12.6 km of 33 kV MV power lines and 7.99 km of 415/240 V LV distribution power lines. Five load centres are served by the electricity distribution network in Rubirizi District. These are: Kyambura TC, Kyenzaza TC,Kirugu TC, Katerera TC and health centre and Kyamwiru Catholic Mission Centre.

There is one bulk metering units and nine transformer sub-stations in the electricity distribution network in Rubirizi District. The transformer sub-stations are detailed below.

  • 5 No. 25 kVA distribution transformers.
  • 3 No. 50 kVA distribution transformers.
  • 2 No. 100 kVA distribution transformers.
  • 1 No. 500 kVA distribution transformer.

The electricity distribution network in Kasese District consists of 104.83 km of 33 kV Medium Voltage (MV) power lines and 166.35 km of 415/240 V Low Voltage (LV) distribution power lines.Thirty nine load centres are served by the electricity distribution network in Kasese District.

These are: Kiburara TC,Kirembo TC,Kisinga TC,Kagando TC and hospital, Nsenyi,Kajwenge,Kaberere,Kyalhumba,Kinyamaseke TC,Munkunyu TC,Kanyampara TC,Bukangara TC,Katholhu TC, Kasanga TC, Mpondwe-Lhubiriha TC, Bunyiswa, Mubawa TC, Kakone TC, Musyenene TC, Karambi TC,Kamasasa TC, Maliba TC, Kacungiro, Rusese, Kalimanga, Kabatunda, Rwansande, Kyabarungira, Kirabaho, Kitswamba, Kajwenge, Nyabirongo, Kyanya, Maliba, MailoKumi, Nyakiyumbu and Rugendabara and environs.

Ongoing Projects

 Electricity Distribution Network

Kilembe Investments Limited’s service territory is the area outside Umeme Ltd’s footprint covering the districts of Kasese, Rubirizi, Buhweju, Mitooma, Sheema and Bushenyi. Kilembe Investments Limited is yet to take over power lines in Buhweju, Mitooma, Sheema and Bushenyi Districts. Power Lines  currently under KIL are:

1. Kikorongo-Bwera-Mpondwe with T-offs to:

  • Kiburara-Kisinga-Nsenyi-Kajwenge-Kyalhumba
  • Kiburara-Rwenguhya
  • Kinyamaseka-Munkunyu-Kanyampara
  • Kinyamaseke-Kasomoro
  • Katholhu-Bunyiswa-Kakone-Musyenene
  • Bwera-Kasanga
  • Bwera-Karambi
  • Lhubiriha-Kamasasa

2. Bugoye-Ibanda-Nyakalingijo with T-offs to Kyanya and Maliba TCs
3. Rugendabara-Kitswamba-Kyabarungira-Kabatunda with T-off to Kithoma
4. Kyambura-Katerera

Upcoming Projects

Future prospects;

  • Covering all the remaining parts of the concession area
  • Lighting the hard-to-reach areas far from the grid by solar energy